This is mostly intended to be a public service mssg. - mostly. I've been building spec (speculation) houses for the last couple of decades now. On average about one a year. The last three have been the same plan, on small acreages I've been fortunate to find. I kept pretty good track of hours and costs on this last one. Here's some numbers.
The house is 1750 sq ft, single story, attached garage.
Permits: the permits for this house in city limits, Eugene/Springfield would be about $24k. My county permit was about $7500.
Excavation: Ex. Subcontractors get around $150-$200 per hr. x approx 10 hrs for cut out and backfill = $2000. - fuel costs; $200. Subs profit $180 hr.
Foundation: I do my own, but concrete subs charge around $35-$40 per lin.ft. (labor and mtl.) x approx 220 lin. ft. perimeter of house = $8800. Material costs; 18 yds, re-bar, etc., approx $3000. $8800 - $3000 = $5800. I had 25 man hours (mhs) in the last foundation. $5800/25 hrs = $232 per hr.
Framing: I spent the 1990's as a framing sub. Back then the going rate was $2 - $5 per sq ft. These days it's closer to $8 - $15. 1750 sq ft x $10 = $17,500. I had approx 130 mhs. $17,500/130 = $134. per hr.
Framing lumber, approx. $18,000. Trusses approx. $7,500.
Windows: Milgard Styleline vinyl. Mtl cost approx $3700.
Siding: We used to get about $2 per sq ft. Now, don't know. But I did recently sub out my MIL's older home with detached garage. Approx 2000 sq ft of siding area. She had gotten other bids of 25k - 30k. My sub did it for $13,500. Mtl. cost approx. $3500. $13.,500 - $3500 = $10,000. I est. he had approx. 60 mhs. $10,000/60 = $166 per hr.
Roofing: This is an area that can be all over the board. Especially with re-roofing contractors. I am talking now, new const. only. My roofing sub works for approx $50 per square. (10'x10') Labor only. If one can't find a sub to do it for close to that, you're not trying hard enough. Mtl. cost, approx. $100 per sq. x 35 sq. =$3500. Labor, approx. 25 mhs. 35 sq. x $50 per sq. = $1750. $1750/25 = $70 per hr.
Plumbing: I have a plumbing sub that works 'cost plus' for rough in only. Most plumbing subs won't do rough in only, but will only bid rough in + fixture set. Rough in only isn't necessarily legal, building code wise, but also isn't necessarily policed by the building inspectors. (I have yet to find a sub that can set a sink or toilet without scratching it or gooping caulk all over everthing) A standard Plumber sub bid for rough in + fix. set will run about $15k. My last house cost, rough in, labor and mtl. was $6500. Mtl. cost, approx. $1500. $6500 - $1500 = $5000. I est. he had 24 mhs. $5000/24 = $208 per hr.
Electrical: This is one area that cannot be gamed. This one is policed by the building dept. The going rate for rough in + fix set is about $6.50 per sq ft. 1750 x $6.50 = $11,375. (this includes wire, etc., but not light fixtures) My guess at mtl. cost is $2375. $11,375 - $1375 = $10000. I est. labor hrs at 70 mhs. $10000/70 = $142 per hr.
Heating: Forced air electric with outdoor heating/cooling unit. These guys bids are generally fairly competitive. This last house went for $13,500.
Insulation: Competitively priced contractors will do this, labor and mtl. for less that you can buy the mtl for at HD. Last house went for $6800.
Drywall: Labor and mtl., hang, tape and texture, the going rate is around $1.25 per sq. ft. of board area. 7000 sq. ft. x $1.25 = $8750. This sub is usually a 'pickup truck' contractor, who isn't hands on, who instead has a hired crew, so I won't est. his profit per hr rate, Same for insulation and heating. I est the mtl cost for drywall and mud at approx $3000.
Painting: Exterior; labor and mtl competitive sub bid; $4000. Definitely do your own when possible. Mtl. cost; 25 gal @ $35 = $875. $4000 - $875 = $3125. My time on the last job - mask, spray, hand paint trim; 16mhs. $3125/16 = $195 per hr. Interior; This is easier as the masking is already done by the drywallers. Sub bid; $3000. Mtl. cost; 20 gal primer @ $18 = $360, 20 gal @ $35 = $700. $700 + $360 = $1060. $3000 - $1060 = $1940. Est. hrs. - 10 mhs. Profit - $194 per hr.
I won't est. the profit per hr rate on this next items as I've never sub'ed them out.
Interior/exterior doors and trim package est cost; 20 int. doors @ $200 = $4000. 2 ext. doors @ $500 = $1000. MDF trim, $1000. Est install time; 60 mhs.
Interior door and trim painting: Mtl. cost; 8 gal @ $35. Est hrs; Forever. But, masking and spraying def gives the best overall look.
Cabinets: Kitchen and bath. $12,000. Install time; 16 mhs.
Flooring: Vinyl plank. 1750 sq. ft. @ $3.50 = $6125. Install time; 24 mhs.
Plumbing fixtures; sinks, wc's disposal, etc. $2500. 10 mhs.
Light fixtures: $2500. Elec. contractor install.
Drives and walks: My sub does this for $1.25 per sq. ft. Place and finish. (I set up the forms.) Approx 1000 sq. ft. @ $1.25 = $1,250. 6 guys for 1hr to place, then 2 guys for 4 hrs to finish - twice = 28 mhs. Pickup contractor profit; Depends on what he pays his guys. Est. average pay rate of $ 20. per hr. 28 hrs x $20 = $560. $1,250 - $560 = $690.
Remember how I started this post with the term "mostly"- Sorry bout this KG.
Realtors: Sale price - $500,000 x 5% commission = $25,000. Est. labor; 1 mhs. $25,000 per hr.
https://photos.zillowstatic.com/fp/3384 ... _1152.webp
https://photos.zillowstatic.com/fp/dc7 ... 152.webp
The house is 1750 sq ft, single story, attached garage.
Permits: the permits for this house in city limits, Eugene/Springfield would be about $24k. My county permit was about $7500.
Excavation: Ex. Subcontractors get around $150-$200 per hr. x approx 10 hrs for cut out and backfill = $2000. - fuel costs; $200. Subs profit $180 hr.
Foundation: I do my own, but concrete subs charge around $35-$40 per lin.ft. (labor and mtl.) x approx 220 lin. ft. perimeter of house = $8800. Material costs; 18 yds, re-bar, etc., approx $3000. $8800 - $3000 = $5800. I had 25 man hours (mhs) in the last foundation. $5800/25 hrs = $232 per hr.
Framing: I spent the 1990's as a framing sub. Back then the going rate was $2 - $5 per sq ft. These days it's closer to $8 - $15. 1750 sq ft x $10 = $17,500. I had approx 130 mhs. $17,500/130 = $134. per hr.
Framing lumber, approx. $18,000. Trusses approx. $7,500.
Windows: Milgard Styleline vinyl. Mtl cost approx $3700.
Siding: We used to get about $2 per sq ft. Now, don't know. But I did recently sub out my MIL's older home with detached garage. Approx 2000 sq ft of siding area. She had gotten other bids of 25k - 30k. My sub did it for $13,500. Mtl. cost approx. $3500. $13.,500 - $3500 = $10,000. I est. he had approx. 60 mhs. $10,000/60 = $166 per hr.
Roofing: This is an area that can be all over the board. Especially with re-roofing contractors. I am talking now, new const. only. My roofing sub works for approx $50 per square. (10'x10') Labor only. If one can't find a sub to do it for close to that, you're not trying hard enough. Mtl. cost, approx. $100 per sq. x 35 sq. =$3500. Labor, approx. 25 mhs. 35 sq. x $50 per sq. = $1750. $1750/25 = $70 per hr.
Plumbing: I have a plumbing sub that works 'cost plus' for rough in only. Most plumbing subs won't do rough in only, but will only bid rough in + fixture set. Rough in only isn't necessarily legal, building code wise, but also isn't necessarily policed by the building inspectors. (I have yet to find a sub that can set a sink or toilet without scratching it or gooping caulk all over everthing) A standard Plumber sub bid for rough in + fix. set will run about $15k. My last house cost, rough in, labor and mtl. was $6500. Mtl. cost, approx. $1500. $6500 - $1500 = $5000. I est. he had 24 mhs. $5000/24 = $208 per hr.
Electrical: This is one area that cannot be gamed. This one is policed by the building dept. The going rate for rough in + fix set is about $6.50 per sq ft. 1750 x $6.50 = $11,375. (this includes wire, etc., but not light fixtures) My guess at mtl. cost is $2375. $11,375 - $1375 = $10000. I est. labor hrs at 70 mhs. $10000/70 = $142 per hr.
Heating: Forced air electric with outdoor heating/cooling unit. These guys bids are generally fairly competitive. This last house went for $13,500.
Insulation: Competitively priced contractors will do this, labor and mtl. for less that you can buy the mtl for at HD. Last house went for $6800.
Drywall: Labor and mtl., hang, tape and texture, the going rate is around $1.25 per sq. ft. of board area. 7000 sq. ft. x $1.25 = $8750. This sub is usually a 'pickup truck' contractor, who isn't hands on, who instead has a hired crew, so I won't est. his profit per hr rate, Same for insulation and heating. I est the mtl cost for drywall and mud at approx $3000.
Painting: Exterior; labor and mtl competitive sub bid; $4000. Definitely do your own when possible. Mtl. cost; 25 gal @ $35 = $875. $4000 - $875 = $3125. My time on the last job - mask, spray, hand paint trim; 16mhs. $3125/16 = $195 per hr. Interior; This is easier as the masking is already done by the drywallers. Sub bid; $3000. Mtl. cost; 20 gal primer @ $18 = $360, 20 gal @ $35 = $700. $700 + $360 = $1060. $3000 - $1060 = $1940. Est. hrs. - 10 mhs. Profit - $194 per hr.
I won't est. the profit per hr rate on this next items as I've never sub'ed them out.
Interior/exterior doors and trim package est cost; 20 int. doors @ $200 = $4000. 2 ext. doors @ $500 = $1000. MDF trim, $1000. Est install time; 60 mhs.
Interior door and trim painting: Mtl. cost; 8 gal @ $35. Est hrs; Forever. But, masking and spraying def gives the best overall look.
Cabinets: Kitchen and bath. $12,000. Install time; 16 mhs.
Flooring: Vinyl plank. 1750 sq. ft. @ $3.50 = $6125. Install time; 24 mhs.
Plumbing fixtures; sinks, wc's disposal, etc. $2500. 10 mhs.
Light fixtures: $2500. Elec. contractor install.
Drives and walks: My sub does this for $1.25 per sq. ft. Place and finish. (I set up the forms.) Approx 1000 sq. ft. @ $1.25 = $1,250. 6 guys for 1hr to place, then 2 guys for 4 hrs to finish - twice = 28 mhs. Pickup contractor profit; Depends on what he pays his guys. Est. average pay rate of $ 20. per hr. 28 hrs x $20 = $560. $1,250 - $560 = $690.
Remember how I started this post with the term "mostly"- Sorry bout this KG.
Realtors: Sale price - $500,000 x 5% commission = $25,000. Est. labor; 1 mhs. $25,000 per hr.
https://photos.zillowstatic.com/fp/3384 ... _1152.webp
https://photos.zillowstatic.com/fp/dc7 ... 152.webp